DAVIDSON COUNTY, I-24
The retracing of pavment markings with spray thermoplastic on various interstates and state routes in Region 3 mm 37-41
· 6/13 – 6/15, 8 p.m. – 6 a.m., There will be lane closures for mobile long line striping operations in both the WB and EB directions on I-24 in Davidson County.
The retracing of pavment markings with spray thermoplastic on various interstates and state routes in Region 3 mm 53-57
· 6/13 – 6/15, 8 p.m. – 6 a.m., There will be lane closures for mobile long line striping operations in both the WB and EB directions on I-24 in Davidson County.
The repair of the bridge on I-24 over Mill Creek MM 58-59
· 6/13 – 6/15, 8 p.m. – 5 a.m., There will be lane closures on I-24 EB and WB over